June 2019

  • TeamDynamix configuration and integration

July 2019

  • TeamDynamix configuration and integration
  • Requirements gathering with Cornell units

August 2019

  • TeamDynamix configuration and integration
  • Requirements gathering with Cornell units

September 2019

  • TeamDynamix configuration and integration
  • Meetings with Cornell units
  • Sandbox user training

October 2019

  • Meetings with Cornell units
  • Non-CIT access to the sand box
  • Sandbox  user training
  • Sandbox administrator training

November 2019

  • Meetings with Cornell units
  • Sand box access for CIT
  • Sandbox user training
  • Sandbox administrator training
  • Non-IT TeamDynamix user training
  • TeamDynamix go live for non-IT units

December 2019

  • Meetings with Cornell units
  • Non-IT TeamDynamix user training
  • TeamDynamix go live for non-IT units

January 2020

  • Non-IT TeamDynamix user training
  • TeamDynamix go live for non-IT units

February 2020

  • Non-IT TeamDynamix user training
  • IT TeamDynamix administrator training
  • IT TeamDynamix user training
  • TeamDynamix go live for non-IT units

March 2020

  • IT TeamDynamix administrator training
  • IT TeamDynamix user training
  • End of remedy automated reporting-March 31, 2020

April 2020

  • TeamDynamix go live for IT units

May 2020

  • TeamDynamix go live for IT units

June 2020

  • Everyone out of Remedy-June 1, 2020